Foundation & Anchor Requirements
The lift is only as secure as the concrete supporting it. Before installation, verify that your floor meets the minimum installation requirements.
Concrete Specifications
- Minimum concrete strength: 3,000 PSI
- Minimum slab thickness: 4-1/4 inches
- Minimum anchor embedment: 3-1/4 inches
Important: The supplied anchors are 3/4" × 5-1/2". If more than 2-1/4 inches of the anchor extends above the finished floor after installation, the anchor does not have adequate embedment.
Anchor Installation Sequence

Figure 1 — Proper installation sequence for supplied expansion anchors.
Foundation Requirements
- Maintain at least 6 inches from any slab edge or expansion joint.
- Minimum anchor spacing: 6-1/2 inches.
- Minimum hole depth: 4-1/4 inches.
- Do not install on asphalt or unstable surfaces.
- Shim columns until plumb before tightening anchors.
- Torque all anchors to 130 ft-lbs.
Let's Talk
If you have questions about your concrete floor or your installation site, we'd be happy to discuss it with you.
Related Learning Center Documents
- Electrical Requirements
- Space Requirements
- Unpacking the Lift
Notice
This Learning Center Document is intended as general guidance. Always follow the current installation instructions supplied with your lift. Specifications and installation requirements may change without notice.
Revision History
| Revision | Date | Description |
|---|---|---|
| 1.0 | August 2026 | Initial publication. |
AutoLifts Learning Center
Learning Center Document AL-LC-106
Revision 1.0
© 2026 AutoLifts.com. All Rights Reserved.
Learning Center Document AL-LC-106
Revision 1.0
© 2026 AutoLifts.com. All Rights Reserved.